First Dussafu DTM-4H Production Well Completed

Published

Panoro Energy announced the successful completion of the DTM-4H well, the first of the phase 2 Tortue development wells, offshore Gabon.

The well was drilled with the Borr Norve jackup drilling rig in 116 meters water depth as a horizontal production well in the Gamba reservoir. A long horizontal section of good quality oil saturated Gamba sands was drilled and completed and the subsea tree installed ready for hook up early next year.

The rig has now moved to the DTM-5H well location, the second of the four phase 2 production wells, and the DTM-5H well was recently spud.

First production from the phase 2 Tortue wells is planned for March 2020 with all four phase 2 wells expected to be online by June 2020.

Current News

Ndungu Full-Field Starts Up Offshore Angola

Ndungu Full-Field Starts Up Of

Norway's 2025 Oil Output Climbs to Highest Level Since 2009

Norway's 2025 Oil Output Climb

AKOFS Offshore Inks New Vessel Deal with Petrobras

AKOFS Offshore Inks New Vessel

UK Trade Body Challenges Government View on North Sea Gas Decline

UK Trade Body Challenges Gover

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine