DNO Wraps Up Offshore Decommissioning Project in UK

Credit: DNO
Credit: DNO

Norwegian oil and gas company DNO said Monday that the wellhead platform production facilities had been removed from the Schooner field offshore UK, in what the company said was the last major offshore operation under DNO’s multi-year North Sea decommissioning program.

The heavy lift was conducted using the Heerema Marine Contractors’ semi-submersible crane vessel Thialf

The 1,200-tonne platform deck was lifted aboard the vessel on May 17, while the jacket was removed on May 23, after the piles had been cut three meters below the seabed. 

The deck and jacket have since been transported to the Hoondert Yard in the Netherlands for dismantlement and recycling.

“We have conducted these operations in a safe, cost-efficient and environmentally responsible manner, coordinating five tier-one contractors and displaying our capabilities as a full life-cycle offshore operator,” said DNO’s Chief Operating Officer Chris Spencer.

In 2019, DNO assumed operatorship and working interest in the Schooner and Ketch fields in the UK and the Oselvar subsea field in Norway, three end-of-life fields whose decommissioning had been deferred by the previous operator.

DNO completed plugging and abandonment (P&A) of the nine Ketch wells and the three Oselvar wells in 2021, followed by the 12 Schooner wells in 2022. The Ketch and Oselvar production facilities were removed and dismantled last year. It is expected that about 95 percent of the removed materials will be recycled.

Current News

Expro Wraps Up Five-Well Subsea Job in Australia

Expro Wraps Up Five-Well Subse

US Drillers Add Oil and Gas Rigs for First Time in Four Weeks

US Drillers Add Oil and Gas Ri

North Sea Energy Firms Look Beyond UK After Tax Squeeze

North Sea Energy Firms Look Be

Sapura Ônix Heads to Atlanta Field to Install Subsea Equipment

Sapura Ônix Heads to Atlanta F

Subscribe for OE Digital E‑News

Offshore Engineer Magazine