Siem axes PSV order due to delays

OE Staff
Wednesday, January 18, 2017

Siem Offshore has canceled the fourth of four dual fueled platform supply vessels (PSVs) shipbuilding-contracts with Remontowa Shipbuilding in Poland, due to delay in the delivery.

“The company is covered with refund guarantees from an international bank for all pre-delivery installments made under the contract,” says Siem Offshore. 

In December 2016, Siem canceled the third of the four PSV order for the same reason. 

The four vessels were ordered in December 2013, and were scheduled to be delivered from Q3 2015 to Q2 2016. 

Categories: Vessels Activity Europe

Related Stories

Cadeler’s WTIV Newbuild Arrives to Rotterdam Ahead of Maiden Job

Bourbon to Support Oil and Gas Major’s Drilling Campaign Off Namibia

Türkiye Offshore Wind Roadmap Outlines Up to 7GW Potential by 2040

Current News

Shipping, Energy Tax Could Help Foot $1T to Combat Climate Change - COP29

Germany Preps for More FSRU Vessels

Oil Steadies as Sverdrup Restart eases Geopolitical Jitters

BP's Whiting IA Refinery Restart Delayed

Subscribe for OE Digital E‑News