Statoil gets Gullfaks B platform extension

OE Staff
Tuesday, June 20, 2017

Statoil’s Gullfaks B platform and associated pipelines will now operate until 30 June 2036 after receiving a consent for use from Norway’s Petroleum Safety Authority (PSA).

PSA’s existing consent for the platform – which was installed in July 1987 and started operations in February 1988 – was set to expire next month. Statoil filed for an extension to extract remaining resources from the Gullfaks field, PSA said in a 20 June press statement.

PSA said it gave consent based on Statoil's documentation of assessments, which conclude that the facility can continue to be operated safely and responsibly and in compliance with regulatory requirements. 

The consent application covers:

  • Gullfaks B
  • 12in oil/gas pipeline from Gullfaks B to Gullfaks C
  • 8in gas pipeline from Gullfaks B to Gullfaks A
  • 16in flexible oil pipeline from Gullfaks B to Gullfaks A
  • 20in water injection pipeline from Gullfaks A to Gullfaks B (not operational, preserved)

Statoil is operator of the Gullfaks field, located in Block 43/10 at Tampen in the northern North Sea. Gullfaks has been developed using three integrated processing, drilling and accommodation facilities with concrete jackets and steel decks, Gullfaks A, B and C.

Earlier this year, Statoil said a discovery it made while drilling from the Gullfaks C platform could contain between 1-3 MMcum of recoverable oil equivalent.

Read more:

Statoil adds to Gullfaks area resources

Categories: North Sea Europe

Related Stories

PXGEO to Keep Sea1 Offshore’s Subsea Construction Vessel on Duty

Axess Group Secures More Work Offshore Norway

Repsol Gets $440K Fine for Halting NEO’s Production at Flyndre Field

Current News

A-O-S Welcomes Its Third CTV for Offshore Wind Market

CIP Inks PPA for 500MW Taiwanese Offshore Wind Project

Lime Petroleum Strengthens Its Norwegian Oil and Gas Portfolio

Red7Marine Assists N-Sea with OW Export Cable Repair in Irish sea

Subscribe for OE Digital E‑News