OTC16: DNV GL unveils P&A RP

OE Staff
Wednesday, May 4, 2016

Norway's DNV GL has issued a new, globally applicable Recommended Practice (RP) forrisk-based plugging and abandonment of offshore wells.

The certificaton and verification society says, in combination with optimized project execution and new technology, the RP could potentially reduce P&A costs by 30–50%. 

The framework outlined in the RP provides the possibility for individualized, fit-for purpose well abandonment designs, a contrast to the prescriptive methodology available in the industry today.

Authorities require that well operators perform safe and environmentally friendly operations by establishing a permanent barrier to prevent release of hydrocarbons to the surface. Traditional P&A methods are time consuming, costly and have remained unchanged despite technological advances in the industry, says DNV GL. 

“The costs related to well P&A are enormous. Using current practices, there will be a global fleet of dozens of full-time drilling rigs needed to perform P&A for generations to come. We believe the time has come to tackle this issue head on by assisting regulators and the industry to establish a new methodology for dealing with the decommissioning of wells. By using this method, hazardous wells will get the attention they deserve, and benign wells will avoid excessive rig-time and expenditure. We're looking at potential cost savings of more than USD32bn on the Norwegian Continental Shelf alone, and even more globally,” says Per Jahre-Nilsen, Business Development Leader, Drilling & Well, DNV GL – Oil & Gas.

The DNVGL-RP-E103 "Risk based abandonment of offshore wells" is based on case studies performed by DNV GL in projects dating back to 2011. A thorough process is defined where the key stages in the risk-based methodology are assessing the well barrier failure modes, well flow potential, valued ecosystem and safety components, dispersion modeling and impact analysis. These steps allow for a consistent method to be applied when assessing risk of the offshore well abandonment designs. The RP methodology provides assurance that selected well abandonment designs are robust, environmentally friendly and economically advantageous.

The main obstruction to change in this sector has been today’s prescriptive approach to the regulations, which represents a conservative interpretation of past experience and outdated technologies, says DNV GL. Practice also differs from country to country. The new RP uses well-known and accepted risk-based approach methodology in which both environmental and safety risk aspects are key factors. Through the development of the RP, DNV GL worked with international oil and gas operators to establish an initial set of risk acceptance criteria and cross-checked these using case studies. The criteria and methodology have been further strengthened through dialogue with regulators and industry players.

Read more

Pain in the annulus 

Categories: Well Operations Decommissioning Wells

Related Stories

Well-Safe Solutions Secures $25M Well Decom Contracts in North Sea

Santos Hires McDermott for Harriet Alpha Decom Work Off Australia

Global OTEC Presents OTEC Power Module for Remote Offshore Platforms

Current News

Oil Edges to 2-Week High on Ukraine News

EMGS to Conduct CSEM Survey Offshore India

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Subscribe for OE Digital E‑News