Sevan rig deferred again

OE Staff
Friday, April 15, 2016

Sevan Drilling and Cosco have agreed to defer delivery of the new-build Sevan Developer cylindrical drilling rig for another six months.

The deepwater unit is being built by Cosco, but has faced construction delays. Meanwhile, Sevan has seen a slowdown in contract awards for deepwater units. 

Sevan had agreed a standstill arrangement with Cosco over the rig. In 2014, the two companies agreed to defer the Sevan Developer's delivery date for 12 months with mutually agreed options, exercisable at six month intervals, extending the delivery date for up to a total of 36 months from 15 October 2014. 

The original delivery date had been 30 April 2014. 

A final delivery installment has been amended to US$473.4 million, representing 90% of the $526.0 million contract price and Cosco will refund $26.3 million, or 5% of the contract price, plus other associated costs to Sevan Drilling by 25 May 2016.

The agreement can be amended further upon the expiration of the option period.

Other terms and conditions under the deferral agreement dated October 2014, including termination rights, remain unchanged.

Categories: Drilling Rigs

Related Stories

Norway Grants Two-Well Drilling Permit to Vår Energi

Sea1 Offshore Secures Work for AHTS Fleet in Australia

Nong Yao C Development Bolsters Valeura’s Production Rates Off Thailand

Current News

OMV Petrom Orders Field Support Vessel for Black Sea Gas Field

New LNG Bunker Vessel for TotalEnergies LNG Bunkering Ops

Dutch Engineering Firms Present Floating Offshore Substation Concept

Saipem Installs Trunkline for Woodside’s Scarborough Gas Project off Australia

Subscribe for OE Digital E‑News