Petronas PFLNG1 construction at 95%

OE Staff
Wednesday, December 30, 2015

The Petronas floating LNG1 (PFLNG1) has reached a 95% overall progress in its construction and will come onstream in 2016, the company said.

In late September, Petronas began lifting the first topside module for its PFLNG1 facility at the Daewoo Shipbuilding and Marine Engineering (DSME) shipyard in Okpo, South Korea. 

The topside module lifting marks another major construction milestone for the facility, as it signifies the near completion of the PFLNG1, which will be the world’s first floating LNG facility in operation.

Once the construction and installation phases are completed in 2015, PFLNG1 will be moored in Kanowit field, which is about 180km offshore Sarawak, Malaysia.

Read more:

Technip wins PFLNG1 tieback work

Categories: Natural Gas Construction FLNG Asia LNG

Related Stories

TechnipFMC Lands Coral North FLNG Contract from Eni

Israel Greenlights Major Natural Gas Deal with Egypt

ADNOC Lines Up $11B for Offshore Hail and Ghasha Gas Project

Current News

Equinor Renews Subsea Inspection Deal with Subsea 7

Saipem Gets DNV Certification for Offshore Asset Lifecycle Management

Archer to Remain North Sea Drilling and Maintenance Duty for Aker BP

Tekmar Secures Over $9M Offshore Wind Cable Protection Deal

Subscribe for OE Digital E‑News