DOF Subsea on Knarr FPSO installation

OE Staff
Thursday, July 25, 2013

DOF Subsea Norway has been awarded a contract by Teekay Petrojarl Production in Norway for work on a newbuild FPSO. 

The scope of work includes mooring pre-installation, tow-out and hook-up work for Teekay Petrojarl Production’s new FPSO, due to be installed on the BG-operated Knarr field in the Norwegian North Sea.

DOF Subsea Norway will mobilize its Skandi Skolten vessel for this project, with six additional vessels from its global fleet being utilized in support.

The project will be completed in three phases, the first of which will see the pre-installation of the complete mooring system, consisting of 12 mooring lines, taking place in 2013.  DOF Subsea has already started with the planning, engineering and offshore management.

The FPSO will be kept at a fjord on the west coast of Norway when it is delivered in 2014 until the field is ready for the FPSO to be installed later in the year, at which time it will be towed out to location and connected to the pre-laid mooring system.  

Jan-Kristian Haukeland, EVP DOF Subsea Atlantic region, said: “The award of this contract means we now have significant project work scopes from Teekay in the Norwegian and UK sectors of the North Sea."

 

Categories: FPSO Europe

Related Stories

Israeli Firm Hires Assistance to Advance Portuguese Wave Energy Project

Aker BP Set for Drilling Ops in Norwegian Sea

Galp’s CEO Filipe Silva Steps Down

Current News

CNOOC Boosts Dongfang Gas Fields Output with New Platform Coming Online

Lawsuit Seeks to Reverse Biden Ban

SouthCoast Wind gets final BOEM nod

Oil set for fourth week of gains on US sanctions

Subscribe for OE Digital E‑News