DEME Offshore has selected tier one suppliers to supply jackets for the foundations of Moray Offshore Windfarm East (MOWEL), located in the Outer Moray Firth, 22km off the coast of Scotland.
According to DEME, formerly GeoSea, Smulders will carry out a major part of the fabrication works on 55 of 100 jackets in Newcastle, including all final assembly, with Lamprell producing the remaining 45.
The balance of the jackets will be supplied by Dubai-based Rig Metals LLC (part of the Lamprell Group) and then shipped and offloaded to northern Scottish ports. A contract was also awarded to PSG Marine & Logistics Ltd which will manage the onshore handling works at the marshalling harbour in Invergordon.
The offshore installation works will be undertaken from northern Scottish ports, including the Port of Invergordon which has been lined up by DEME Offshore to act as a staging facility under a multi million pound contract.
DEME Offshore has also awarded the fabrication of 150 pin piles to the Scottish company BiFab, now owned by Canadian DF Barnes. The remaining piles have been awarded to the German fabricator EEW. Furthermore, the specialised UK-based davit crane supplier Granada is lined up to supply over 100 offshore cranes for the project.
In the coming months, DEME Offshore, together with its partner Smulders, will organise Tier Two local supply chain workshops to identify and contract other work packages with local suppliers.
Jan Klaassen, Business Unit Manager Offshore Renewables, comments: “We are pleased to announce that after a long and carefully executed procurement process we have been able to award a significant amount of work to both the Scottish and English supply chain. We are very much looking forward to working with the highly skilled experts in the local offshore wind supply chain and developing partnerships for future potential projects in this flourishing sector."
The 950 MW wind farm is being developed by Moray Offshore Windfarm East Ltd (MOWEL) which is a joint venture company owned by Diamond Green Limited (33.4%), EDPR (33.3 %), ENGIE (23.3%) and CTG (10%).The project was initiated following the award of a £57.50/MWh Contract for Difference (CfD) by the UK Government in 2017.
DEME Offshore’s announcement of Tier One suppliers for its EPCI works marks the culmination of around 1.5 years of work, which it carried out under an early works’ contract for the design and procurement of 100 wind turbine foundations, plus three offshore substation platform foundations. DEME Offshore will perform the transport and installation of each of the foundations and the three topsides for the offshore substation platforms.