The transmission system operator Tennet has moved the first submarine cable from the Dutch wind farm zone "Borssele" to the transformer station.

"TenneT has laid the first sea cable to connect the Alpha platform to the transformer substation in Borssele. In the morning of Friday 12 April, VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation," said a press release.

The cable-laying vessel, Giant 7, then repositioned itself in the Honte and started with the most critical part of the installation: crossing the fairway.

Before crossing the channel, shipping traffic to and from the port of Antwerp was blocked until Sunday afternoon. The crossing went completely according to plan and the traffic got back on track in the course of the evening.

In the coming weeks, preparations will be made to also connect the second sea cable for the Borssele Alpha project to the transformer station.

Categories: Energy Wind Power Transmission/Gears Subsea Cables

Related Stories

Tekmar Secures Over $9M Offshore Wind Cable Protection Deal

Equinor Books Odfjell Drilling’s Deepsea Aberdeen Semi-Sub Rig

Orbital Marine Power Secures $9.31m Investment

Current News

Equinor Renews Subsea Inspection Deal with Subsea 7

Saipem Gets DNV Certification for Offshore Asset Lifecycle Management

Archer to Remain North Sea Drilling and Maintenance Duty for Aker BP

Tekmar Secures Over $9M Offshore Wind Cable Protection Deal

Subscribe for OE Digital E‑News