Tennet Relocates Submarine Cable from Borssele

Laxman Pai
Wednesday, April 17, 2019

The transmission system operator Tennet has moved the first submarine cable from the Dutch wind farm zone "Borssele" to the transformer station.

"TenneT has laid the first sea cable to connect the Alpha platform to the transformer substation in Borssele. In the morning of Friday 12 April, VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation," said a press release.

The cable-laying vessel, Giant 7, then repositioned itself in the Honte and started with the most critical part of the installation: crossing the fairway.

Before crossing the channel, shipping traffic to and from the port of Antwerp was blocked until Sunday afternoon. The crossing went completely according to plan and the traffic got back on track in the course of the evening.

In the coming weeks, preparations will be made to also connect the second sea cable for the Borssele Alpha project to the transformer station.

Categories: Energy Wind Power Transmission/Gears Subsea Cables

Related Stories

US Judge Proposes CITGO Auction Solution

Euro Oil Giants Rethink Renewable Balance

UK Approves Five Subsea Power Cable Projects

Current News

Danos Leaders Recognized in “40 Under 40” Lists

ExxonMobil to Drill for Gas Off Cyprus in January

Mocean Energy Raising Funds to Advance Wave Energy Tech

Seadrill’s Drillships Getting Ready to Start Work Off Brazil

Subscribe for OE Digital E‑News