TechnipFMC OSV Refit Completed

Wednesday, June 26, 2019

The TechnipFMC-owned diving support vessel Deep Arctic has departed Damen Shiprepair Amsterdam on time following a significant maintenance stopover, a substantial proportion of which was spent in dry dock.

According to the shipyard, the project was exceptionally complex, with a total of 2,198 work permits issued, an indication of the large number of individual jobs that were completed and the number of stakeholders involved.

The 156-meter vessel came to Damen Shiprepair Amsterdam (DSAm) primarily for a main class renewal (intermediate) docking and for maintenance including the renewal of the steel plates to its box coolers. To achieve this the yard removed 31 separate box coolers from the forward, midships and aft sea chests. The preparations needed to accomplish this involved the disconnection of all the associated piping on both the coolers and the anodes, the removal of any associated deck plates and benches, and the installation of lifting pad eyes above the box coolers where required.

(Photo: Damen)

Following the secure and precise removal of the coolers according to a pre-prepared lifting plan, they were placed either on the floor of the dock, on the quayside, or into shipping crates specially fabricated by DSAm for transport to the owners’ own specialists. Once all the overhauls and inspections were completed and the coolers returned, the yard reinstalled them all. The works required renewing the box cooler steel plates included cropping the old sea chest plates and replacing them with new steel plates prefabricated in the DSAm steel workshop and machine shop.

Once the works were complete, all the interior areas affected, including the ballast water tanks, forward tanks, coffer dam tanks and hull plates, were treated with a coatings program. The yard also blasted and painted all the repaired sea chests and 16 additional forward sea chests.

(Photo: Damen)

While in dry dock, Deep Arctic also received a complete thruster overhaul including upgrades to the tunnel, retractable and Azimuth thrusters, six in total. The vessel's propeller shaft and center line rudder also had their 10-yearly overhaul. These operations all took place in collaboration with the owner’s specialists Rolls Royce and OEM. Additional associated works included the fabrication of new piping for both tunnel thrusters, renewal of the lower gear units, repairs to the rudder stock actuator and the overhaul of the stern tube seal boxes.

The yard said it also performed a large number of works at considerable heights. These included repairs to the gangway and load tests on the accommodation ladder and platform. Maintenance was also done to the structures of cranes no.1 (400T) and no.2 (58T), which included the removal of rust and painting the main and navigation masts and the helideck support structure.

(Photo: Damen)

Categories: Offshore Vessels Industry News ROV & Dive Support

Related Stories

DeepOcean Lands Its Largest IMR Contract to Date for Equinor’s Norwegian Assets

Vestdavit Supplies Davits for Ulstein Newbuild CSOV

Bourbon to Support Oil and Gas Major’s Drilling Campaign Off Namibia

Current News

Oil Edges to 2-Week High on Ukraine News

EMGS to Conduct CSEM Survey Offshore India

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Subscribe for OE Digital E‑News