Nord Stream 2 Pipe Ends Link Underway

Tuesday, August 13, 2019

The Saipem pipelay vessel Castoro 10 (C10) is currently on location offshore Rügen, Germany to tie together the two ends of a Nord Stream 2 pipe string laid last year on the seabed.

The two sections will be connected above water with a weld seam, project operator Nord Stream 2 said on Monday.

In what is known as an Above-Water Tie-In (AWTI) both pipe ends will be lifted out of the water and then cut, aligned and welded together from a working platform attached to the C10. The weld seam is ultrasonically tested and coated with an anti-corrosion protection. Afterwards, the pipe string will be placed on the Baltic seafloor in a slight arc.

Including all preparation and follow-up work, the procedure takes two to three weeks. With optimal weather conditions and smooth operations, the works above water can be completed within just a week.

The C10 is situated northwest of the Landtief approach and positioned with eight anchors. Due to the anchor pattern as well as diving works, a safety distance of at least 1,000 meters from C10 must be observed.

Work on the Nord Stream 2 Pipeline continues to proceed as scheduled. Altogether more than 1,700 kilometers (over 70%) of both pipe strings have been laid in accordance with the existing permits in the waters of Germany, Sweden, Finland and Russia.

Categories: Vessels Engineering Pipelines Pipelay Vessel

Related Stories

Cadeler’s Nexra Lines Up O&M Campaign in Taiwan

Solstad Lines Up Work for Normand Tonjer CSV

Strategic Marine Delivers CTV for Taiwan’s Offshore Wind Sector

Current News

Transocean to Acquire Valaris for $5.8B

ADNOC, RWE Explore LNG Supply Deal as Germany-UAE Deepen Ties

Eni’s Congo LNG Phase 2 Begins Exports with First LNG Cargo (Video)

Perenco Installs Kombi-II MOPU Offshore Congo

Subscribe for OE Digital E‑News