Nord Stream 2 Pipe Ends Link Underway

Tuesday, August 13, 2019

The Saipem pipelay vessel Castoro 10 (C10) is currently on location offshore Rügen, Germany to tie together the two ends of a Nord Stream 2 pipe string laid last year on the seabed.

The two sections will be connected above water with a weld seam, project operator Nord Stream 2 said on Monday.

In what is known as an Above-Water Tie-In (AWTI) both pipe ends will be lifted out of the water and then cut, aligned and welded together from a working platform attached to the C10. The weld seam is ultrasonically tested and coated with an anti-corrosion protection. Afterwards, the pipe string will be placed on the Baltic seafloor in a slight arc.

Including all preparation and follow-up work, the procedure takes two to three weeks. With optimal weather conditions and smooth operations, the works above water can be completed within just a week.

The C10 is situated northwest of the Landtief approach and positioned with eight anchors. Due to the anchor pattern as well as diving works, a safety distance of at least 1,000 meters from C10 must be observed.

Work on the Nord Stream 2 Pipeline continues to proceed as scheduled. Altogether more than 1,700 kilometers (over 70%) of both pipe strings have been laid in accordance with the existing permits in the waters of Germany, Sweden, Finland and Russia.

Categories: Vessels Engineering Pipelines Pipelay Vessel

Related Stories

Strategic Marine Delivers Offshore Crew Transfer Vessel to AES

Subsea7 Secures IRM Job at Türkiye’s Sakarya Gas field

First Russian Ice-Class LNG Carrier Hits Water

Current News

BOEM Boosts Monetary Penalties for Oil & Gas firms

Portugal Selects Four Offshore Wind Farm Sites Ahead of Auction

Technical Issue Shuts Down BP’s Caspian Sea Gas Platform

Kazakhstan Orders Kashagan Oil Field Operator to Pay $6.6M Fine

Subscribe for OE Digital E‑News