First 2 Jackets for NFE Project Completed

Laxman Pai
Thursday, November 28, 2019

State-owned Qatar Petroleum has announced the completed fabrication of the first two jackets required for offshore facilities as part of its North Field Expansion (NFE) Project.

Saad Sherida Al-Kaabi, the Minister of State for Energy Affairs, the President and CEO of Qatar Petroleum, and Chairman of the Qatargas Board of Directors, said: “The successful, on-schedule completion of the first two jackets is a testament to our commitment to putting the various NFE project components in place, on time, and with the highest safety and quality standards.”

Al-Kaabi added, “I would like to congratulate Qatargas and McDermott on this milestone achievement and to thank their collaboration with Qatar Petroleum in building these jackets in such a short time.”

A ceremony was held to mark this significant milestone in Batam, Indonesia, in the presence of Sheikh Khalid bin Khalifa Al Thani, Chief Executive Officer of Qatargas, His Excellency Mr. Amer Mohd Al Theyab, Chargé d'Affaires of the State of Qatar in Indonesia, and executives from Qatar Petroleum, Qatargas and McDermott.

Sheikh Khalid said, “I would like to congratulate everyone at Batam and the entire NFE team for safely and successfully delivering these first two jackets.  It was very challenging to meet our schedule for sail-away and I have been delighted with the drive, teamwork and flexibility demonstrated by everyone to meet this goal. It clearly portrays the shared values of Qatargas and McDermott in areas of safety, quality, and high-caliber workforce.”

Highlighting the outstanding safety performance, the Qatargas’ CEO said, “I am delighted to note that this has been achieved safely, with over 1 million man hours without any lost time Injuries.  Everyone can be rightly proud of what has been achieved.”

The NFE project’s Engineering, Procurement, Construction and Installation contract for the jackets was awarded to McDermott in April 2019. McDermott was also awarded the Front End Engineering and Design contract for the associated topsides and pipelines in May 2019.

As the World’s Premier LNG Company, Qatargas has a well-proven track record of delivering such major projects, and in operating various onshore and offshore facilities in the North Field with world-class reliability and operational excellence.

Categories: Offshore Energy Gas Construction Fabrication

Related Stories

Ocean Kinetics, Green Marine UK complete OpenHydro Decommissioning

Brunvoll Thrusters for REM Offshore

Ørsted Awards Multi-Million Dollar Contracts for Hornsea 3 OW Farm

Current News

BOEM Okays New England Offshore Wind Project

Solstad Offshore Bolsters Ownership Stake in Omega Subsea

DeepOcean Takes Over Equinor’s Pipeline Repairs Contract from TechnipFMC

Petrobras Steps Closer to Developing Hydrogen Plant Powered by Renewables

Subscribe for OE Digital E‑News