DEME Hits Halfway Mark with Borssele Wind Farm Installation

OE Staff
Friday, April 10, 2020

Offshore installation company DEME Offshore has said made strong progress with the installation of the foundations for offshore wind turbines at Ørsted’sBorssele 1 & 2 Offshore Wind Farm in the Dutch North Sea, reaching the halfway mark. 

Having started construction works with offshore installation vessel ‘Innovation’ in mid-January 2020, foundation installation has hit the halfway mark, with 47 out of a total of 94 foundations installed, DEME said Thursday.

"Despite significant weather downtime in February the installation of the foundations is on schedule for completion in early June. The large carrying capacity of ‘Innovation’, efficient jacking operations and smooth offshore bolting operations lead to record installation cycles," DEME said.

“Together with Ørsted, we will continue our excellent partnership for the remaining foundations. I also would like to take this opportunity to thank the client, our crew and project staff for the great achievement, considering the unprecedented challenges they were all facing,” says Bart De Poorter, General Manager DEME Offshore.

The Borssele 1 & 2 offshore wind farm will be completed in 2020.

Categories: Energy Vessels Industry News Activity Europe Construction Installation The Netherlands Offshore Wind

Related Stories

Vard Secures Five Vessels Order for Oil and Gas Sector

Norwind Offshore Takes Delivery of Vard-Built CSOV

Masdar, SOCAR and ACWA Set Sights on 3.5GW Offshore Wind Projects in Azerbaijan

Current News

ExxonMobil to Drill for Gas Off Cyprus in January

Mocean Energy Raising Funds to Advance Wave Energy Tech

Seadrill’s Drillships Getting Ready to Start Work Off Brazil

New Alliance Targets CTV Deliveries for Japanese Offshore Market

Subscribe for OE Digital E‑News