BW Offshore Liquidates Subsidiary after FPSO Stuck in New Zealand for Months

Friday, October 23, 2020

Oslo-listed FPSO leasing specialist BW Offshore is liquidating its New Zealand subsidiary operating the FPSO Umuroa, stuck in New Zealand for months after the termination of the charter and the liquidation of its client Tamarind Resource. 

Tamarind had in October 2019 informed BW the charter for 2007-built Umuroa FPSO at the Tui oil field offshore New Zealand, would end on December 31, 2019. BW then said it would disconnect and remove the FPSO from the field by the end of March 2020. 

However, the removal of the 232 meters long FPSO was then stopped as the environment protection regulators wanted all of the subsea equipment removed from as well, something which is, per BW, the responsibility of the (now insolvent) Tamarind.

Liquidating to prevent further losses

Now, in a statement late on Thursday, BW Offshore said that the Board of Directors of its subsidiary BW Umuroa Pte. Ltd. (BWU), owner and operator of the FPSO in New Zealand, resolved to place the company into voluntary liquidation to prevent further losses.

In the announcement, BW reminded that Tamarind went into insolvency in December 2019, without any funding secured for decommissioning and abandonment liabilities. 

In March 2020 the New Zealand Government, through the Ministry of Business, Innovation and Employment (MBIE), assumed full responsibility for the decommissioning of the field and for disconnection of the FPSO, BW Offshore said.

"After almost a year of continuous efforts to reach an agreement relating to the disconnection of the FPSO or get cost covered to stay on the field until MBIE is able to execute field decommissioning, the directors and shareholder of BWU have been left with no choice but to place the company into voluntary liquidation in order to prevent further accumulation of unsustainable losses," BW Offshore said.



Following the liquidation of Tamarind in 2019, BW Offshore said that BWU has paid in full the expenses involved in maintaining the FPSO on location and in compliance with all regulatory requirements. This has included full remuneration of the local crew and payments to suppliers. BWU will ensure that no contracted party or crew member is left out of pocket as a result of the steps it has been forced to take, the company said.

“We have assumed responsibilities far beyond the scope of the contract to ensure the safety and integrity of the vessel, and the protection of the environment, pending an agreement with MBIE to move ahead with the FPSO disconnection”, said Marco Beenen, the CEO of BW Offshore.

'Victim' of Tamarind's Insolvency

According to BW Offshore, MBIE has publicly recognized that BWU is a victim of the insolvency of the field operator Tamarind.

“We have not been able to reach an agreement with MBIE which provides a viable solution despite significant efforts from our side, which includes offering to plan and execute the disconnection for MBIE at cost and without any profit”, said Marco Beenen

“As it now stands, in addition to a significant accumulated cost, we are still incurring more than USD 1 million per month to keep the FPSO Umuroa in compliance with regulatory requirements, and this cost is expected to increase as time progresses. This is unsustainable for us as a company," Beenen said.

According to BW Offshore, the FPSO Umuroa has been, and presently remains, safely moored to the Tui field, and BW Offshore will work with the liquidators to ensure the safety of the crew, the integrity of the FPSO, and continued care and respect for the environment. 

"The FPSO no longer contains crude in the tanks and has minimum amount of fuel onboard to ensure a safe transition to the liquidators," the company said.

Overall, BW has said it has incurred more than $21 million in 2020 alone to keep the FPSO on site and in compliance with regulatory requirements during the period, including demobilization costs for the earlier attempt to disconnect the vessel. 

Worth noting, BW said that after the termination of the FPSO contract by Tamarind in 2019, and subsequent insolvency, BW Offshore has not received any payments due under the contract for more than 12 months.

"At the end of the contract, 31 December 2019, this amounted to USD 31 million. All unpaid invoices have already been provided for," BW said.

Liquidators to take control

As a result of the voluntary liquidation, BW Offshore said,  the liquidators will take into custody and control all the assets and property of BWU, and apply them in satisfaction of BWU’s liabilities to its creditors. 

"BW Offshore will no longer have control over FPSO Umuroa. Consequently, it is expected that the remaining net book value of USD 21 million on the unit will be written down to zero," BW Offshore said.

The FPSO Umuroa, converted to a FPSO from a 1981-built tanker, has an oil processing capacity of 50,000 b/d, and a gas handling capacity of 25 mmcf/d. It can store 775,000 barrels of oil.

Categories: Energy Activity FPSO Production Floating Production Australia/NZ

Related Stories

Norway's O&G Production Beats Expectations

LR and SHI Join Forces for Green Ammonia FPSO System

SBM Offshore and Technip Energies to Build TotalEnergies’ GranMorgu FPSO

Current News

Oil Edges to 2-Week High on Ukraine News

EMGS to Conduct CSEM Survey Offshore India

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Subscribe for OE Digital E‑News