Allseas Removes Gyda Platform Topsides

Friday, June 3, 2022

Allseas' giant Pioneering Spirit vessel recently removed the 18,400-tonne former drilling and production facility Gyda from the Norwegian North Sea in a single lift, and brought it ashore in Norway for disposal.

Under a contract by Repsol, Allseas is also booked to remove the massive 11,200 t Gyda jacket, later this summer. 

Gyda is a field in the southern part of the Norwegian sector in the North Sea, between the Ula and Ekofisk fields. The field was developed with combined drilling, accommodation, and processing facility supported by a steel jacket standing in 66 m water depth. 

The platform started producing in 1990, and a decommissioning plan was submitted in 2016.


Categories: Energy North Sea Activity Decommissioning

Related Stories

Woodside to Shed Some Trinidad and Tobago Assets for $206M

Woodside to Shed Some Trinidad and Tobago Assets for $206M

NEO Energy and Repsol to Merge UK Oil and Gas Assets

NEO Energy and Repsol to Merge UK Oil and Gas Assets

DNO Finds Oil and Gas in Northern North Sea

DNO Finds Oil and Gas in Northern North Sea

Current News

Valeura’s Assets in Gulf of Thailand Remain Operational After Earthquake

CIP Orders Vestas Offshore Wind Turbines for 495MW Taiwanese Project

First Turbine Stands Tall at RWE’s Sofia Offshore Wind Farm

Bardex Corporation, Gabriel Engineering Partner Up for Floating Wind Moorings

Subscribe for OE Digital E‑News

Offshore Engineer Magazine