Grant Agreement Reached for $157m Blyth Subsea Cable Facility

Wednesday, June 15, 2022

JDR Cable Systems (JDR) reached final agreement under the UK government’s Offshore Wind Manufacturing Scheme (OWMIS) on financial support for its new subsea cable manufacturing facility in Cambois, near Blyth, Northumberland.

The agreement means JDR is on track to begin construction in summer 2022, with a planned opening in 2024. The $157m UK Export Finance (UKEF) Export Development Guarantee is set to create 171 high-quality local jobs on completion while safeguarding 270 jobs at JDR’s existing facilities.

JDR has also announced a $3.6m investment into its existing facility at Hartlepool, with the installation of a new vertical layup machine (VLM). The VLM is nearly double the weight capacity and increases production capacity at Hartlepool by approximately 25 per cent, readying the facility for manufacture of array cables above its current 66 kV product range, with the addition of 132kV and 150kV cabling planned at the facility.

Categories: Technology Offshore Wind Cables

Related Stories

BOEM Finalizes Offshore Wind Fisheries Mitigation Guidance

Bibby Marine Inks Shipbuilding Contract for eCSOV with Spanish Shipyard

DEME, Van Oord Secure Offshore Wind Work in Taiwan

Current News

Naval Fleets power Vestdavit's record 2024 sales

China's CNOOC Aims for Record Oil and Gas Production in 2025

Equinor Hires BW Offshore and Altera Infrastructure for Bay du Nord FPSO Job

All Set for Construction of RWE’s Offshore Wind Control Center in Germany

Subscribe for OE Digital E‑News