Crane on Tyra II Process Module Now in Permanent Use

OE Staff
Tuesday, December 27, 2022

Norwegian Energy Company (Noreco) said Friday it had reached a milestone on the hook-up and commissioning campaign of Tyra II with the crane on the process module (the "TEG") now in permanent use. 

"The milestone was planned for early Q1 2023 and is as such achieved ahead of schedule despite the challenging weather conditions earlier this month," Noreco said.

According to Noreco, the TEG crane is important for the project as it enables an efficient completion of the remaining scope of the hook-up, commissioning, and start-up of Tyra II.

Due to seabed subsidence, the Tyra field required a redevelopment, calling for the removal and decommissioning of the prior Tyra platforms, reuse, and a 13-meter extension of the existing jackets at six platforms, and the construction and installation of new topsides, a new processing platform, and a new accommodation platform.

In October, TotalEnergies, the project operator, said that it had completed the offshore installation works at the Tyra II field redevelopment project in the Danish North Sea. This was related to the installation of new facilities.

Earlier this month,  TotalEnergies said that the old platforms had been recycled.

First gas from Tyra II is slated for the winter season 2023/24


Categories: Energy Engineering North Sea Industry News Activity Europe Construction Cranes

Related Stories

OMV Gets North Sea Drilling Permit

SouthCoast Wind gets final BOEM nod

Danos Names Habbit Decommissioning Ops Manager

Current News

Lyondell to begin closure of Houston Refinery this weekend

RODA responds to Trump EO on Offshore Wind & Permitting

EnQuest to Acquire Harbour Energy's Vietnamese Assets

Petrobras Extends Tupi Field FPSO Stay, Lines Up System Upgrades

Subscribe for OE Digital E‑News