Equinor's Hammerfest LNG plant in Arctic Norway suffered a compressor failure on Thursday and is expected to remain offline until May 19, Norwegian gas system company Gassco said in a regulatory note on Friday. 

The outage was caused by a technical problem with a heat exchanger that occurred during a restart of the plant following a one-day maintenance outage, an Equinor spokesperson said. 

The plant will remain offline until repairs have been carried out, the spokesperson added. Hammerfest LNG, also known as Melkoeya, has capacity to deliver about 6.5 billion cubic metres (bcm) of gas per year, enough to cover energy demand for about 6.5 million European homes, or 5% of all Norwegian gas exports, Equinor has said. 

Norway is Europe's largest supplier of natural gas following a sharp reduction in Russian deliveries amid the war in Ukraine. 

The Melkoeya plant receives its gas via a pipeline from the offshore Snoehvit gas field and is owned by operator Equinor (36.79%) as well as Petoro (30%), TotalEnergies TTEF.PA (18.40%), Neptune Energy (12%) and Wintershall Dea (2.81%). 

(Reuters - Reporting by Terje Solsvik and Nora Buli; Editing David Goodman and Jan Harvey)

Categories: Energy LNG Coastal/Inland Industry News Activity Europe Production Barents Sea

Related Stories

Harbour Energy Concludes Wintershall Dea Deal and Raises Production Outlook

Oil Production Starts at Aker BP’s Tyrving Field

Namibia: The Newest Most Promising Deepwater Rig Demand Hotspot

Current News

New England States Move Forward with Three Giant Offshore Wind Farms

Subsea7 Reveals it is Supporting Shell's Vito Waterflood Project

Norway Attracts 21 Bidders in Latest Oil and Gas Exploration Round

EU Grants Over $20M for Pilot Wave Energy Farm Offshore Portugal

Subscribe for OE Digital E‑News