Petrobras' Anna Nery FPSO Starts Production

Monday, May 8, 2023

Brazilian oil firm Petrobras said Monday that the FPSO Anna Nery started production on Sunday, May 7, 2023, in the  Campos Basin.

The FPSO is part of the revitalization project of the Marlim and Voador fields, which will produce the post-salt reservoirs and Brava, located in the pre-salt of the two fields.

The unit can produce up to 70,000 barrels of oil daily and process 4 million m³ of gas.

Jean Paul Prates, CEO of Petrobras, said:"This is the largest project in the world in the recovery of mature assets in the offshore industry. Through it, we will increase production, maintain jobs, and open an important learning and knowledge front for other similar projects throughout Brazil."

The Anna Nery FPSO and the Anita Garibaldi FPSO make up the first major revitalization project for mature fields in the Campos Basin.

"The deployment of these two new production systems, appropriate to the mature field exploration format, provides operational continuity to the Marlim and Voador fields, increasing production to an average of 150,000 barrels of oil equivalent per day (boed), maintaining jobs and support services, and opening an important learning and knowledge front for other revitalization projects," Petrobras said.

The FPSO Anna Nery, supplied by Malaysia's Yinson, is anchored in a water depth of 927 meters and interconnected to 32 wells, with peak production scheduled for 2025. 

The Marlim and Voador revitalization project will contribute to the recovery of the Campos Basin production, currently at about 560,000 boed. The projection for the basin's production is 900,000 boed in 2027.

The production startup also marks the start of the firm charter of the Anna Nery FPSO for a period of 25 years, until 2048.

"The delivery of the asset is a laudable achievement amid challenges brought about by the Covid-19 pandemic and disruptions to the global supply chain. FPSO Anna Nery is YP’s first operational asset in Brazil. YP is currently also constructing two more Brazil-bound assets, which are both on track for completion in 2024," Yinson said.

Yinson Production's Chief Executive Officer Flemming Grønnegaard said:"Every challenge faced during construction was met with unwavering energy and passion of the people involved.  The excellent teamwork – between Yinson Production’s project and corporate teams, project partnes
Sumitomo, contractors, classification society, sub-contractors, and banking partners – was the most significant driver leading to the project’s success. We are honored to contribute to Brazil’s local energy landscape through the provision of affordable and reliable energy to its economy and communities.”

Categories: Energy Activity FPSO Production Floating Production

Related Stories

AI & Offshore Energy: The Higher the Stakes, the More Value AI Creates

Expro Teams Up with Petrobras for New Well Flowmeter Tech

Shell to Add Two Wells at GoM Perdido Platform

Current News

BOEM Okays New England Offshore Wind Project

Solstad Offshore Bolsters Ownership Stake in Omega Subsea

DeepOcean Takes Over Equinor’s Pipeline Repairs Contract from TechnipFMC

Petrobras Steps Closer to Developing Hydrogen Plant Powered by Renewables

Subscribe for OE Digital E‑News