Eirin Development: Equinor Selects Moreld Apply for Gina Krog Topside Upgrades

Wednesday, October 18, 2023

Norwegian engineering firm Moreld Apply has won a topside tie-in contract with the Norwegian oil firm Equinor in relation to its Eirin offshore field development.

Two new wells from the Eirin field will be tied back to the Gina Krog platform through a flexible flowline. To be able to process the wet gas, several topside modifications are needed. The work consists of modifications to the existing facilities in addition to the integration of new equipment.

Moreld Apply's main scope includes a new inlet cooler and separator for wet gas; metering for both gas and liquids; pull-in and hang-off of a new umbilical from Eirin; new HPU and MEG skids for subsea supply; and hook-up operation for subsea power and control.

The project's anticipated scope entails approximately 220,000 manhours, and work has already started, with completion expected by the fourth quarter of 2025.

Nine Andresen, VP Maintenance & Modifications, adds, "Together with Equinor, we have matured Eirin in record time. The contract format in FLX promotes efficiency, high innovation,and collaboration. We are now planning to deliver the project ready for production start as early as 2025, a challenging but essential contribution to delivering necessary energy with associated low emissions to Europe."

Moreld Apply defines this award as a significant contract worth 0.5 to 1.5 billion Norwegian kroner.

The Eirin gas field, discovered in 1978, holds estimated recoverable reserves of 27.6 million barrels of oil equivalent, with natural gas as the predominant component.

Categories: Energy Engineering Industry News Activity Europe Production

Related Stories

Equinor to Axe 250 Jobs as Part of Renewables Unit Streamlining

Cadeler’s WTIV Newbuild Arrives to Rotterdam Ahead of Maiden Job

Global OTEC Presents OTEC Power Module for Remote Offshore Platforms

Current News

Velesto Completes Removal of Wrecked Naga 7 Jack-Up Rig Off Malaysia

Saudi Aramco Suspends Another Shelf Drilling Jack-Up

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

SBM Offshore Secures $1.5B Financing for FPSO Jaguar

Subscribe for OE Digital E‑News