Offshore energy infrastructure construction firm Malaysia Marine and Heavy Engineering (MMHE) has delivered the Central Processing Platform (CPP) topside to oil company SapuraOMV for the SK408W Jerun gas field, located offshore Sarawak in Malaysia.

With the weight of approximately 15,000 MT, the CPP topside underwent meticulous crossover and sailaway operations on February 25, 2024, showcasing an astounding 10.5 million man-hours without a single lost time injury (LTI).

The structure will be installed together with its 11,200 MT jacket at the Jerun development project offshore Bintulu in Sarawak. SapuraOMV is the operator of SK408W Block, with Shell and Petronas Carigali holding 30% equity interest, each.

Upon the completion of installation, Jerun CPP will produce ACQ of 550 MMSCFD, where the condensate will be spiked into the Jerun gas stream for comingled export to shore using a new export pipeline which is routed towards the existing E11R-B platform, currently operated by SK Gas, according to MMHE.

The delivery of the topsides is part of the contract SapuraOMV and MMHE signed in 2021, which covers the construction and installation of platform and pipelines for the project.


Categories: Engineering Industry News Activity Asia Gas Oil and Gas

Related Stories

TotalEnergies and Oil India to Jointly Tackle Methane Emissions Issues

Keppel Reclaiming Control of 13 Rigs to Cash In on Offshore Drilling Market's Growth

Panoro Energy and GEPetrol Sign PSC for Block Offshore Equatorial Guinea

Current News

Danos Leaders Recognized in “40 Under 40” Lists

ExxonMobil to Drill for Gas Off Cyprus in January

Mocean Energy Raising Funds to Advance Wave Energy Tech

Seadrill’s Drillships Getting Ready to Start Work Off Brazil

Subscribe for OE Digital E‑News