Dorado’s FID Delayed as Reshaping of Project Aims to Reduce Its Total Capital Outlay

Thursday, July 18, 2024

Carnarvon has informed that the joint venture in charge of Dorado project, one of the largest offshore oil discoveries in Western Australia, is finalizing the assessment of key optimization opportunities, expected to improve project economics and significantly lower upfront CAPEX, ahead of final investment decision (FID) rescheduled for 2025.

The joint venture in charge of Dorado project is between Santos (80%, operator), Carnarvon (10%) and OPIC Australia, affiliate of Taiwan’s CPC Corporation, (10%).

According to the latest update, the joint venture continues to make positive progress towards finalizing the material economic improvement opportunities for the Dorado project.

These include an opportunity to optimize the production rate, allowing the joint venture to reduce the sizing of the floating production offtake and storage (FPSO) vessel, Wellhead Platform (WHP) and other facilities, and phase the timing of wells.

Reducing the facility capacity is expected to reduce the overall Capital Expenditure (CAPEX) for the Phase 1 liquids development.

Phasing the development wells and reducing the number of wells required prior to first oil allows the joint venture to further reduce the up-front CAPEX prior to first oil. Any remaining wells would be drilled during production allowing them to be funded through project cash flows. These opportunities are expected to considerably improve the project’s economics and reduce the time to first oil.

The joint venture is also assessing FPSO vessel redeployment options along with other donor hulls for FPSO conversion. Dependent on the suitability and availability of these units, there could be further cost savings and opportunities to reduce the time to first oil for the project above those already outlined.

The joint venture is taking the requisite time to fully evaluate these potential opportunities. Given the impact on engineering design and cost of utilizing this potentially lower cost option, FEED re-entry is planned for later this year once the joint venture secures the best option vessel or hull.

Importantly, any design changes would be within the scope of the approved Offshore Project Proposal (OPP). This allows the operator to leverage the previously completed FEED work for the optimized development FEED re-entry later this year, with FID expected in 2025.



Along with the engineering and design work to allow the Dorado Phase 1 liquids development to progress to FID, work is ongoing for the requisite Environment Plans (EPs) that are necessary to progress the project.

The EPs for drilling and completion, and WHP and subsea systems installation are in progress, with the external consultation work expected to be visible in the coming quarter.

The joint venture has already secured a Production License and Offshore Project Proposal, ensuring that all primary project approvals will be secured following the approval of the relevant EPs.

Based on the project optimizations, Carnarvon estimates that the overall CAPEX prior to first oil will be below the previous guidance of approximately $2 billion.

“I am pleased with the progress the Dorado project has made and am excited by the reshaping of the project, which is expected to reduce the total capital outlay by Carnarvon.

“While the FID timing is slightly later than previously envisaged, the joint venture is taking the requisite time to assess the optimization and FPSO redeployment opportunities, and to materially progress EP approvals prior to FID. These are important activities which require additional time and are expected to unlock considerable value for shareholders.

“Carnarvon’s estimates for up-front capital expenditure savings are expected to be material to the Company. With the company’s $115 million (A$176 million) cash balance, $90 million development funding cost carry and optionality for a prospective debt facility, Carnarvon expects to be fully funded for its share of development costs to first oil under the optimized project,” said Carnarvon CEO, Philip Huizenga.

Categories: Industry News Activity Australia/NZ Oil and Gas

Related Stories

Final Pluto Train 2 Modules for Scarborough Gas Project Arrive to Australia

Noble Secures Work in Ghana and Gulf of Mexico for Its Drillship Pair

Expro Lands Contract to Support 52-Well P&A Campaign

Current News

Offshore Drilling 2025: 3 Things to Watch During a Year of Market Corrections

Chevon’s Sanha Lean Gas Connection Project Achieves First Gas off Angola

BP and Partners Secure Rights for 450MW Offshore Wind Farm in Japan

JERA-Led Consortium to Develop Japan’s 615MW Offshore Wind Project

Subscribe for OE Digital E‑News