Second Oil Train for Energean Power FPSO Completes Lift-Off (Video)

Tuesday, October 29, 2024

Oil and gas company Energean has lifted the second oil train for its floating production, storage, and offloading (FPSO) unit operating in the Mediterranean Sea, offshore Israel.

The post-lift, installation and commissioning activities are expected to take up to six months to complete, with liquids production expected to increase to 20-25k bbl/d in the second half of 2025.

The Energean Power FPSO, moored 80 kilometers west of Israel's coast, has four production wells in operation at Karish field.

In Februrary 2024, Energean brought its Karish North and second gas export riser online, enabling the utilization of the FPSO’s maximum gas capacity, which stands at 8 bcm/yr.


“We are very pleased to announce that following an intense period of collaborative work with our contractors and the Israeli authorities, the M10 2nd oil train module has been lifted onto the Energean Power FPSO, following a successful offloading from the port of Limassol.

“This operation demonstrates our commitment to both our clients and a broad range of stakeholders and to regional energy security - M10 will enhance our ability to provide secure and reliable energy production to the East Mediterranean,” Energean said in a statement.


Categories: Technology Industry News Activity Mediterranean Sea Middle Eeast Oil and Gas

Related Stories

Inpex Secures Environmental Approval for Indonesia’s Abadi LNG Project

Shell Starts Multi-Well Drilling Campaign off Egypt with Stena Drillship

OneSubsea Gets Gullfaks Subsea Compression Upgrade by Equinor

Current News

Ndungu Full-Field Starts Up Offshore Angola

Norway's 2025 Oil Output Climbs to Highest Level Since 2009

AKOFS Offshore Inks New Vessel Deal with Petrobras

UK Trade Body Challenges Government View on North Sea Gas Decline

Subscribe for OE Digital E‑News