Ithaca Energy's delayed Greater Stella Area development remains on track for first production in Q2 next year. In a trading update this morning, Ithaca says sailaway of the FPF-1 floating production facility from the Remontowa Shipyard in Gdansk…
Image from Lundin Petroleum. Lundin Norway, as operator for production license 708, has received consent to drill exploration well 7130/4-1 in the Barents Sea. Drilling is scheduled to begin in November 2015 and estimated to last 56 days…
Tullow Oil's TEN development project offshore Ghana is about 75% complete and on schedule and on budget to deliver first oil in mid-2016, the firm said this morning. The floating production, storage and offloading vessel for the project…
A team from diesel power specialist Royston has completed the engine overhaul on the Bluewater-owned Haewene Brim floating production, storage and offloading (FPSO) vessel. The facility has operated in the Pierce field in the UK sector of the North Sea since 1999…
UK-based independent Premier Oil says it has lined up key 'world class' contractors to provide the vessel and infrastructure for its Falklands Islands Sea Lion development, after completing pre-front end engineering and design on the project…
Petronas has laid the keel of its second floating LNG vessel, the Petronas Floating LNG2, in Geoje Island, South Korea. JGC Group and Samsung Heavy Industries (SHI), the consortium leading the engineering, procurement, construction, installation and commissioning of PFLNG2…
Cyberhawk Innovations completed its first ROAV inspection of a cargo oil tank on an operational floating, production, storage, and offloading (FPSO) vessel. The inspection took place on board the Gryphon FPSO, owned and operated by Maersk Oil in the UK North Sea…
The North Sea’s first producing oilfield, Argyll, has finally been brought back on stream by operator EnQuest, after being started and decommissioned twice in the past by previous operators. Argyll, now named Alma, and part of EnQuest’s Alma/Galia development…
Fred Olsen Energy has formally declared that construction contract for a newbuild semisubmersible rig which was originally destined for development drilling at the Chevron-operated Rosebank oil development in the UK West Shetlands region has been cancelled…
Dana Petroleum's Western Isles floating production unit will not be on stream until late 2017, some two years later than originally planned, it was confirmed today. In a statement, China's Cosco Corp (Singapore) said it and a European…
JX Nippon Oil and Gas Exploration (Malaysia) has awarded Technip a subsea contract for the Layang field, Block SK10, offshore Sarawak, Malaysia. The contract covers the engineering, procurement, fabrication, installation and commissioning of three flexible pipes totaling 9…
African focussed exploration and production firm Addax Petroleum has extended its contract with Malaysia's Yinson Holdings for use of a floating production, storage and offloading (FPSO) vessel. The Knock Adoon FPSO has been working on the Antan field offshore Nigeria…
Technip has awarded SBM Offshore a front-end engineering and design (FEED) contract for three, large-scale turret mooring systems associated with the proposed Browse FLNG development offshore Australia. The three, large-scale turrets…
BP's Glen Lyon floating production, storage and offloading vessel (FPSO) is nearly finished and due to sail away to the North Sea next month, BP has said in posts on social media. The firm, which posted a video of the naming ceremony…
PTT Exploration & Production International (PTTEPI) has contracted high specification tender barge rig, EDrill-2, for a firm term of 18 months with an option period of 30 months. Zawtika Development Drilling Campaign (Phase 1B + Infield…