Hummer delayed due to weather

Published

Castex Offshore has experienced delays in its Hummer project due to recent weather events in the Gulf of Mexico, according to partner Petsec Energy.

Hummer production platform. Image from Petsec.

First production, which was anticipated for late Q3 2017 in early October, has now been moved to mid- to late-November.

Setbacks for the project also include equipment delays, and the completion of the modifications to the four pile deck. The estimated date to complete construction and be ready for loadout is now mid-October, Petsec says.

The Hummer field extends over Main Pass Blocks 270, 273, and 274. The discovery well, Main Pass 270 #3 BP 1, is about 50mi southeast of Venice, Louisiana, at about 215ft water depth.

Read more:

Castex sets Hummer first oil for Q3

Hummer start-up planned for mid-2017

Current News

Precision Shaft Alignment: A Sustainable Advantage in Modern Engineering

Precision Shaft Alignment: A S

Aquaterra Energy Gets Multi-Year Well Intervention Job off Spain

Aquaterra Energy Gets Multi-Ye

Two DOF Vessels Get Work in North Sea and Australia

Two DOF Vessels Get Work in No

Seatrium Unit Launches Arbitration Against Petrobras over FPSO Contract

Seatrium Unit Launches Arbitra

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine