Danos completes skid fabrication for Appomattox

Published

Danos has completed the fabrication of three boarding valve skids and one service line skid for Shell deepwater Appomattox facility. Requiring approximately 12 months to complete, the project engaged four Danos service lines, including project management, fabrication, coatings, and automation.

Image from Danos.

The skids, weighing in at approximately 160 tons each, were fabricated at Danos’ 120,000sq ft facility in Amelia, La. Coordinating the complex, customer-furnished items required extensive planning and support from each of the company’s service lines, especially its project management team.

Key design elements of the modules included 12,200 psi design pressure and 350˚F operating temperature requirements. The API 15K psi piping system consisted of 4130 material overlaid with Inconel 625. All welding was completed on the project with less than 0.45% weld-repair rate. Indoor humidity-controlled painting habitats were utilized. The project was delivered on budget and was performed safely with no lost time due to accidents or injuries.

“Delivery of this project marks Danos’ entry into the module fabrication market,” said Mark Danos, vice president of project services. “We are proud that Shell chose us as their contractor for this critical component of the Appomattox project.”

Danos was awarded the contract last year in August.

Read more:

 

Danos wins Appomattox contract

Current News

Precision Shaft Alignment: A Sustainable Advantage in Modern Engineering

Precision Shaft Alignment: A S

Aquaterra Energy Gets Multi-Year Well Intervention Job off Spain

Aquaterra Energy Gets Multi-Ye

Two DOF Vessels Get Work in North Sea and Australia

Two DOF Vessels Get Work in No

Seatrium Unit Launches Arbitration Against Petrobras over FPSO Contract

Seatrium Unit Launches Arbitra

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine