Multi-tasking on Solan

Premier Oil’s Solan field is due to come onstream by the end of this year. It’s a unique project for the North Sea – a normally unmanned facility with a subsea oil storage tank.

Bibby Polaris on location at Premier Solan. Images from Bibby.

In February 2013, Bibby Offshore was awarded a contract by Premier Oil to provide subsea support during the Solan facilities installation phase. The work involved utilizing a number of vessels from Bibby’s fleet to maximize uptime and vessel utilization.

Solan

Solan was discovered in the 1990s, in Block 205/26a of the UK Continental Shelf, in 135m water depth,but remained inactive until Chrysaor took it over as part of the UK Government’s Fallow Field initiative and drilled appraisal wells in 2008 and 2009. Premier Oil then farmed-in in 2011. 

The steel jacket supported platform at the Solan field has been designed to produce a flow rate of 28,000 b/d, peaking at up to 35,000 b/d across a 20-year lifeline.

The production facility has been developed as a not permanently manned installation (NPMI), and will be operated remotely from an onshore control room in Aberdeen. The topsides facility supports produced fluid separation, gas treatment, all necessary utilities and power generation.

The field infrastructure also includes a 10,000-tonne subsea oil storage tank (SOST) capable of storing 300,000 bo. Produced oil is sent to the SOST before being exported, via a single anchor loading system (SAL), to shuttle tankers.

Bibby Offshore was brought in to perform installation of the subsea infrastructure and, recognizing the challenging environment, came up with a plan to minimize downtime caused by short weather windows.

Preparation is Key

Concrete Matresses on back deck of Bibby Polaris

To mitigate the impact of weather on down time, Bibby Offshore completed detailed weather analysis prior to mobilization to allow a realistic expectation of the potential downtime that could be experienced. The project team also gathered regular forecasts from various sources to help build an accurate picture in the short-term on how the weather would impact over a two-five day window.

Bibby Offshore was also able to take a flexible, multi-vessel approach to the project, making use of several of the vessels in its fleet. The dive support vessel (DSV) Bibby Polaris was used extensively to complete much of the dive works. The DSV Bibby Sapphire and DSV Bibby Topaz and the construction support vessel (CSV) Olympic Ares also made significant contributions to the project. Further to this the company used short-term chartered remotely operated vehicle support vessel (ROVSV) and a third-party DSV.

The multi-vessel approach helped Bibby tailor vessel capabilities to the technical challenges presented by the development and the flexible timeline required to complete the task in line with the client’s program. Crucially, it also helped to prevent any schedule slippages in order to maintain progress towards achieving first oil.

A Phased Approach

The project was planned in two phases. Phase one saw the Olympic Ares carry out installation activities for the SAL, metrology, lay through spool removal, flexible and umbilical installation and wet storing of fabricated spools. Phase two consisted of the diving support operations to complete installation, tie in, stability/protection and recommissioning of the flexible, umbilicals, spools and storage tank.

Offloading System GRP protection cover top section

Each phase of the project had its own challenges. Due to adjustments in the schedule, Bibby Offshore successfully change-managed the scheduled fleet workloads to accommodate Premier Oil’s requirements, resulting in the project becoming multi-phased with additional vessel support.

During the campaign, a 72in structure pile was installed to secure the offloading system to the seabed, which required a large 90-ton “Fast Frame” to be deployed to the seabed. The loading hose itself presented a range of engineering considerations to the project team, due to the inflexibility of the product and the fact it could not be pre-installed on a deployment reel onshore prior to installation on this occasion.

After completing the acoustic metrology, the Bibby Polaris was deployed to connect the pipeline to the SAL spool and the SAL to the offloading hose.

During the offshore operations, the project team configured an optimized deck layout on the Olympic Ares, creating the required working space. This was necessary due to a multi-reel drive system taking up a significant amount of deck space and also the additional equipment required to install flexible and umbilical products before completing metrology between the newly installed platform and subsea oil storage tank. In subsequent campaigns, two DSVs and one ROVSV were mobilized to carry out spool installations, flexible and umbilical tie-ins, mattressing and general storage tank works. 

Current News

Cadeler’s WTIV Newbuild Arrives to Rotterdam Ahead of Maiden Job

Cadeler’s WTIV Newbuild Arrive

LR and SHI Join Forces for Green Ammonia FPSO System

LR and SHI Join Forces for Gre

BP, Equinor, Shell and TotalEnergies Pledge $500M to Boost Energy Access

BP, Equinor, Shell and TotalEn

Seatrium Delivers Fifth Jack-Up to Borr Drilling

Seatrium Delivers Fifth Jack-U

Subscribe for OE Digital E‑News

Offshore Engineer Magazine