Statoil Mariner jacket installation

In this video, Norwegian giant Statoil shows the installation of its largest-ever built jacket for one of its project, the Mariner project.

The steel jacket for Statoil’s Mariner platform on the UK Continental Shelf has now been placed on the field, approximately 150km east of Shetland.

The 22,400-tonne mariner jacket, which stands some 134m high, with an 88m x 62m footprint, had sailed some 1835nm on the S44 barge to the North Sea from the Spanish Dragados yard, in Cadiz, on 10 August.

The S44 barge then launched the jacket, ballasted to a certain angle to enable the 22,400-tonne structure to slide horizontally into the sea. The structure was then upended and maneuvered into the right position using the heavy-lift vessel Saipem 7000.

The jacket will ultimately be secured by 24 piles to ensure that it is safely fixed for many decades to come.  

Read more:

North Sea mega-Mariner jacket installed

Mariner jacket moving on to North Sea

Mariner marches on

Current News

Did You Know? Six Steps Cyber Attackers Take to Steal Maritime Data

Did You Know? Six Steps Cyber

RWE Picks Home Port for Construction of Denmark’s Largest Offshore Wind Farm

RWE Picks Home Port for Constr

Halliburton Misses Profit Estimate Following Damaging Cyber Attack

Halliburton Misses Profit Esti

Türkiye Offshore Wind Roadmap Outlines Up to 7GW Potential by 2040

Türkiye Offshore Wind Roadmap

Subscribe for OE Digital E‑News

Offshore Engineer Magazine