Cidade de Itaguai arrives at Iracema Norte

The Cidade de Itaguaí FPSO has anchored in the Iracema Norte area of Lula field, Petrobras announced on 3 July.

MODEC in consortium with Schahin was responsible for converting the VLCC Alga into the FPSO, as well as constructing and integrating the modules, and operating the unit under 20-year charter.

The FPSO measures 332m long, 31m high, and 58m wide, and weighs 82,000-tonne. The Cidade de Itaguaí is capable of processing 150,000 bo/d, 280 MMscf/d of gas. It is capable of storing of 1.6 MMbbl of total fluids, and injecting 264,000 b/d of water.

Petrobras says oil production at the Iracema Norte field, which is in exploration block BM-S-11 in the pre-salt layer of Santos basin, off Rio de Janeiro, is scheduled to begin in 3Q 2015.

Moored 240 km off the coast of Rio at a water depth of around 2240m, the Cidade de Itaguaí FPSO will be connect to eight production wells and nine injection wells. The natural gas will be exported to shore via a subsea gas pipeline.

Petrobras said that 65% of Cidade de Itaguaí was produced domestically, and 12 of its modules were built in Brazil: 10 at the EBE shipyard in Itaguaí, Rio de Janeiro; and two at the Schahin shipyard in São Sebastião, São Paulo. The modules were integrated at the BrasFELS shipyard in Angra dos Reis, Rio de Janeiro.

Petrobras operates the BM-S-11 area with a 65% interest. Its partners include BG E&P Brasil (25%) and Petrogal Brasil (10%).

Image: Petrobras News Agency

Current News

Oil Edges to 2-Week High on Ukraine News

Oil Edges to 2-Week High on Uk

EMGS to Conduct CSEM Survey Offshore India

EMGS to Conduct CSEM Survey Of

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Poland to Open New Areas for O

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Swedish Firm Eyes Multi-Megawa

Subscribe for OE Digital E‑News

Offshore Engineer Magazine