Edvard Grieg topside complete

The 22,000-tonne topside for the new offshore platform for the Lundin Norway-operated Edvard Grieg field is ready for delivery, in line with the contract awarded three years ago.

Image of the Edvard Grieg project. From Lundin.

Lundin ordered the topside as a complete EPC delivery from Kvaerner in 2012. In addition to delivering the topside as agreed, the project also had a high share of work performed in Norway. The Norwegian value creation from both Kvaerner and subcontractors totals around 70% of the delivery.

The Edvard Grieg field is located in the Utsira High area in the central North Sea.

The topside consists of a main deck module, a combined utility module and living quarters, a process module and a flare tower. The main deck module and the combined utility module and living quarters have both been moved to barges at Stord, ready for tow-out to the field. The process module is also ready on a barge at Aker Solutions in Egersund, Norway, and the flare tower is completed and ready for delivery directly offshore from the subcontractor in Poland.

The modules for the topside will be towed to field and lifted in place on top of the steel jacket in three separate lifts. Kvaerner will assist Lundin with offshore hook up and completion during the summer and into the fall. The production is expected to reach a peak of 100,000 b/d. The oil will be processed and transported through a new pipeline to the Grane field and further via Grane's piping to the Sture terminal.

The next phase for the topside is preparations for tow-out and thereafter hook-up of all systems before production starts offshore. The construction phase now being completed started 3 May 2012 when Lundin Norway signed a letter of intent of around US$1 billion (NOK 8 billion) with Kvaerner for the complete EPC delivery of the Edvard Grieg platform topside. In addition, Kvaerner was awarded the contract to assist Lundin in preparing the platform for production when both the steel substructure, as well as all parts of the topside has been installed at the field.  

Under a separate EPC contract, Kvaerner also delivered the steel jacket substructure for the Edvard Grieg platform. The 14,500-tonne structure was delivered as agreed in the spring of 2014 from Kvaerner's specialized facilities for steel jackets in Verdal, Norway.

For the construction of the Edvard Grieg topside, Lundin selected an execution model that leveraged the Norwegian supplier industry's core competence of delivering complex platforms according to schedule, specifications and contracts, despite high complexity. Kvaerner has as the main contractor utilized Norwegian companies like Aker Solutions and Apply Leirvik as important subcontractors for engineering; and construction of the process and living quarter respectively. Partners in Norway and Europe have in addition delivered pre-fabrication of steel sections and equipment packages. 

The project has contributed to considerable ripple effects for the Norwegian supplier industry as well as for the suppliers' local communities. More than 150 large and small businesses have been involved. At peak, the project employed approximately 7,500 people directly and indirectly. The contract party, Kværner Stord AS delivers revenues of several billion NOK annually, and around 85% of the business' revenues are contracted with Norwegian registered companies during an average year.

“This has been a demanding project but we have kept the milestones all the way, and we are proud of completing Edvard Grieg at the exact time agreed with Lundin Norway three years ago,” says Jan Arve Haugan, Kvaerner president and CEO. “The topside is not only delivered on time but also to agreed quality and exceptionally little outstanding work.”

Lundin Norway is operator and owns 50% of the license. The other partners are Wintershall Norway (15%), OMV Norway (20%) and Statoil (15%).

Current News

Oil Edges to 2-Week High on Ukraine News

Oil Edges to 2-Week High on Uk

EMGS to Conduct CSEM Survey Offshore India

EMGS to Conduct CSEM Survey Of

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Poland to Open New Areas for O

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Swedish Firm Eyes Multi-Megawa

Subscribe for OE Digital E‑News

Offshore Engineer Magazine