VBMS completes umbilical installation

Published

VBMS completed a remote platform tieback project - platform L8-P4 to L6-B - for Wintershall Noordzee B.V. in the North Sea.

Image of the Ndurance. From Boskalis.

The scope of work for VBMS included the engineering, installation and burial of a 19.5km umbilical, at a water depth of 29m.

The L6-B platform is a remote tieback to L8-P4 in the L blocks in the Dutch sector of the North Sea, located approximately 30km northwest of Den Helder. The platform is the newest addition to the Wintershall offshore assets in this sector.

The J-tube pull-ins were performed directly from the Boskalis cable-laying vessel Ndurance using its quadrant system without any interruption or temporary lay-down of the umbilical. VBMS deployed a specialized burial vessel for the post-installation jet trenching. A follow-up as-laid survey of the umbilical route verified that the burial exceeded the requirements in order to ensure optimal protection of the umbilical.

Current News

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

BOEM Initiates Process for Pot

Jumbo Scoops Two Offshore Wind Contracts

Jumbo Scoops Two Offshore Wind

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

Wood Nets Long-Term Maintenanc

TechnipFMC to Supply Subsea Systems for Chevron’s Gas Project off Australia

TechnipFMC to Supply Subsea Sy

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine