Go-ahead for Premier's Catcher

Premier Oil's central North Sea Catcher field development plan has been approved by the UK Department of Energy and Climate Change. 

The Catcher area is expected to produce 96MM boe, with a peak production rate of around 50,000 bo/d.

The development project will comprise 22 subsea wells (14 producers and eight water injectors) on the Catcher, Varadero, and Burgman fields. These will be tied back to a leased FPSO. Oil will be offloaded by tankers, while the gas will be exported through the SEGAL facilities.   

All major service contracts have been awarded and the project is now in the execution phase. First oil is targeted for mid-2017.  

Simon Lockett, Premier Oil's CEO, said: “Having discovered Catcher in 2010, we are extremely pleased to have brought the Catcher area through the development approval process. Once on-stream this project, which has been facilitated by the government’s small field allowances, will underpin our growing cash flows.”  

Read more:

Subsea 7 wins Catcher prize

BW Offshore seals Catcher deal

Aibel bags Catcher topsides

Picture from Aibel. 

Current News

Sea1 Offshore Sells 2014-Built Offshore Construction Vessel

Sea1 Offshore Sells 2014-Built

Pair of China-Built Offshore Wind Vessels Enter Fleet

Pair of China-Built Offshore W

BW Energy Takes FID for Golfinho Boost Project off Brazil

BW Energy Takes FID for Golfin

EnerMech Gets Anasuria FPSO Services Job in North Sea

EnerMech Gets Anasuria FPSO Se

Subscribe for OE Digital E‑News

Offshore Engineer Magazine