Record PIG run on Nord Stream

Nord Stream has completed what is has described as a record-setting PIG run by running a pipeline inspection guage (PIG) along a 1224km route over 10 days.

The run was to carry out a comprehensive inspection of the internal condition of both the Nord Straem pipelines, as part of its long-term safety and pipeline integrity management strategy. 

The PIG, at 7m-long and weighing more than 7-tonne, was sent through the pipeline from Russia to Lubmin, Germany, collecting high resolution data on material integrity while travelling at 1.5m/sec propelled by the gas pressure.

Nord Streamm says it was the first time that a pipeline of this length and with a wall-thickness of up to 41mm had been analyzed in this way. 

For the inspection run, a device with one of the strongest magnetic fields was developed by ROSEN Group in Lingen, Germany.

The “intelligent PIG” has an array of electronic sensors, which screen the material integrity and the geometry of the pipeline.

The PIG has collected over one Terabyte of data on its journey from Russia, and the data was recorded at a rate equivalent to 12 Megabits/sec, 30 times faster than cellular data networks. 

The high-resolution measurement technology can detect smallest changes in the condition of the pipelines. The exact geographical position of the pipelines is also being documented.

The first evaluation of the results confirms that the pipelines have moved only minimally while being operated under full pressure and that there has been no corrosion or deformation.

In 2012 and early summer of 2013, Nord Stream had already examined the external condition of both pipelines. This external visual and instrumental inspection of the pipeline was conducted via remotely operated vehicles (ROVs) followed by support vessels.

The results of the internal and external inspections form the baseline data for regular inspection cycles in the coming years. This will allow any potential changes in the position of the pipes, minimal corrosion and even the smallest mechanical defects to be detected at an early stage.

Image: The "intelligent PIG", courtesey Nord Stream.

Current News

BOEM Okays New England Offshore Wind Project

BOEM Okays New England Offshor

Solstad Offshore Bolsters Ownership Stake in Omega Subsea

Solstad Offshore Bolsters Owne

DeepOcean Takes Over Equinor’s Pipeline Repairs Contract from TechnipFMC

DeepOcean Takes Over Equinor’s

Petrobras Steps Closer to Developing Hydrogen Plant Powered by Renewables

Petrobras Steps Closer to Deve

Subscribe for OE Digital E‑News

Offshore Engineer Magazine