Production resumes at Troll C

Production on the Troll C platform in the North Sea has been resumed, following a shutdown on 15 November due to corrosion found in some tanks on the auxiliary system for treating gas.

"A great effort has been made during the weekend to plan the repair work, and we have also looked into alternative production methods," says Rune Adolfsen, head of production on Troll C.

Adolfsen said Statoil arrived at a solution involving reinjection of untreated gas into the reservoir. Production was resumed during the night between Saturday and Sunday.

"We assume that this method will allow us to produce at around 70% of full capacity during the repairs," Adolfsen said.

The duration of the repair work has not yet been clarified.

Current News

Offshore Wind RoRo Vessel Rotra Futura Launched

Offshore Wind RoRo Vessel Rotr

Oil and Gas Output Trended High Before and After Trump

Oil and Gas Output Trended Hig

Eni Readies Second FLNG for Congo

Eni Readies Second FLNG for Co

QatarEnergy Boosts Offshore Stakes in Namibia

QatarEnergy Boosts Offshore St

Subscribe for OE Digital E‑News

Offshore Engineer Magazine