Albatros Topside Installed

Published

The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)
The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)

The topside of the offshore substation at the Albatros wind farm offshore Germany was installed Tuesday evening, developer EnBW said.

The heavy-lift jack-up vessel (HLJV) Pacific Ospray had loaded the topside in Rotterda, and once in the construction area, the HLJV Innovation lifted the topside on the foundation (monopile and transition piece) that had already been installed. 

The Pacific Ospray will be jacked up and remain next to substation until outstanding coating and welding work is completed.

Afterwards, the jack-up vessel Seafox2 will come to commission the offshore substation.

Current News

Venterra Company, CAPE Holland, Awarded Contract for Fengmiao Offshore Wind Farm

Venterra Company, CAPE Holland

Bae Systems Launches Incubator Program to Propel Technologies Beyond Defense

Bae Systems Launches Incubator

DOF Group ASA Contract Award for Well Intervention Services in North America

DOF Group ASA Contract Award f

Jacket Loadout Milestone Completed for BorWin6 Offshore HVDC Platform

Jacket Loadout Milestone Compl

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine