Leviathan Platform Starts Voyage to Israel

(Image: Delek Drilling)
(Image: Delek Drilling)

The gas platform for the Leviathan natural gas field is on its way to Israel from the Gulf of Mexico, the partners in the project said on Sunday.

The first of four barges transporting the production structure units has left Texas and the other three will set sail in the coming weeks. In September, all the units will be installed on the jacket of the platform already in place 10 kilometers from Israel's shore.

After connecting the units to the platform, Noble Energy, one of Leviathan's partners, will start a series of commissioning tests before initiating commercial gas flow to the domestic market before the end of 2019.

Earlier this month, testing of a subsea natural gas pipeline to Egypt was completed, in the wake of a deal to export $15 billion in gas to a customer in Egypt.

Leviathan, with 22 trillion cubic feet of reserves, was discovered in 2010 and is one of the world’s largest gas discoveries of the past decade. 


(Reporting by Steven Scheer; Editing by Tova Cohen)

Current News

DOF Hooks FPSO Installation Job Off Africa

DOF Hooks FPSO Installation Jo

Brava Energia, Shell Agree Oil Sale from Atlanta Field

Brava Energia, Shell Agree Oil

OKEA Takes Stake in Aker BP-Operated Tverrdal Prospect in North Sea

OKEA Takes Stake in Aker BP-Op

First Foundations for 1.6GW German Offshore Wind Project Reach Dutch Port

First Foundations for 1.6GW Ge

Subscribe for OE Digital E‑News

Offshore Engineer Magazine