Montara Umbilical Cables Replaced

(Photo: Jadestone Energy)
(Photo: Jadestone Energy)

Independent oil and gas company Jadestone Energy said replacement subsea umbilical cables have been installed at the Montara complex, offshore Australia.

The project to replace the umbilical cables, which provide electrical power and control signals to the Montara complex subsea well-heads, was identified by the previous operator PTTEP as a high priority, however the work was deferred until operatorship was transferred.

Jadestone, which took over as operator and 100% owner of the Montara project in 2018, said its operating and engineering team was able to complete this work on budget and without incident.

The replacement umbilical cables were installed using the DOF Subsea vessel Skandi Hercules, which was mobilized in Singapore on August 19, 2019, and completed work infield at Montara on September 22, 2019.

Jadestone said it expects the replacement umbilical to last for the remaining life of the field.

Paul Blakeley, Jadestone Energy President and CEO, said, “Early on, we recognized the need to replace the control link to the Montara subsea wells, and this was done as soon as possible, following acceptance of Jadestone’s safety case for Montara. I think of this as a one-off maintenance project, and having it completed now will provide greater confidence in our ability to deliver guidance volumes from Montara.”

Current News

Oil Edges to 2-Week High on Ukraine News

Oil Edges to 2-Week High on Uk

EMGS to Conduct CSEM Survey Offshore India

EMGS to Conduct CSEM Survey Of

Poland to Open New Areas for Offshore Wind Development in Baltic Sea

Poland to Open New Areas for O

Swedish Firm Eyes Multi-Megawatt Wave Energy Farm Off Grenada

Swedish Firm Eyes Multi-Megawa

Subscribe for OE Digital E‑News

Offshore Engineer Magazine