Jan De Nul Completes Formosa 1 Phase 2

Jan De Nul Group has finished installing foundations, power cables and scour protection on the 120MW second phase of the Formosa 1 offshore wind farm off the coast of Taiwan.

According to the company that provides services related to maritime infrastructure and which has its financial headquarters in Luxembourg, it took four months to complete the engineering, procurement, construction and installation (EPCI) contract, which included installing the project’s 20 turbine foundations.

Formosa 1 (Phase 2) Offshore Wind Farm is owned by Formosa 1 Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%), located in Miaoli County, Taiwan.

Around the monopile foundations 56,000 tonnes of scour protection have been installed. In addition, seventeen inter array cables and three subsea export cables of 33kV were designed, procured, installed, buried, terminated and tested. On land, the connection with the substation was made through 12 km of land power cables.

In addition to some international service and product providers, Jan De Nul Group engaged and contracted various service and subcontract agreements with local companies in Taiwan.  

In addition to using  the Port of Taichung as a marshaling harbor , Jan De Nul Group utilized the local supply chain for quarried rock production, rock load-out operations, storage and transport of the foundation structures, beach pull assistance works, dive support supply, various support vessels, installation of transition joint bays, HDD ducts, land cables installation, and many other minor services.

Peter De Pooter, Manager Offshore Renewable at Jan De Nul Group said: “Our local integration in Taiwan has been ongoing for the last 20 years thanks to our various maritime activities throughout the region. In the past year, we have signed different agreements with local suppliers for this project in Taiwan. Leveraging the local supply chain fits perfectly in our philosophy of involving local companies as much as possible in offshore wind construction.”

Jan De Nul Group had its first project in Taiwan in 1995. Since 1999 the Group has been at work nonstop offering its services to the offshore oil and gas industry, as well as to the main Taiwanese ports (Taipei, Taichung, Kaoshiung and Mailiao).

With two other Offshore Wind Farms currently underway with completion in 2020 and 2021 respectively, Jan De Nul Group continues to play a leading role in Taiwan’s renewable power generation future.

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises of 2 phases: an earlier phase 1 of two wind turbines with a total capacity of 8MW.

A second phase added 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 is the first commercial-scale offshore wind farm in Taiwan before 2020.

The monopiles range from 752 to 1,230 tonnes with a maximum diameter of 8.4 meter and a length ranging from 60.1 to 79.5 meter. The transition pieces weigh 465 tonnes and consists of five internal platforms, an external platform and boat landing.

Current News

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

BP Greenlights $7B CCUS Scheme

SBM Offshore Secures $1.5B Financing for FPSO Jaguar

SBM Offshore Secures $1.5B Fin

Danos Leaders Recognized in “40 Under 40” Lists

Danos Leaders Recognized in “4

ExxonMobil to Drill for Gas Off Cyprus in January

ExxonMobil to Drill for Gas Of

Subscribe for OE Digital E‑News

Offshore Engineer Magazine