DEME Hits Halfway Mark with Borssele Wind Farm Installation

Image Credit: DEME Offshore
Image Credit: DEME Offshore

Offshore installation company DEME Offshore has said made strong progress with the installation of the foundations for offshore wind turbines at Ørsted’sBorssele 1 & 2 Offshore Wind Farm in the Dutch North Sea, reaching the halfway mark. 

Having started construction works with offshore installation vessel ‘Innovation’ in mid-January 2020, foundation installation has hit the halfway mark, with 47 out of a total of 94 foundations installed, DEME said Thursday.

"Despite significant weather downtime in February the installation of the foundations is on schedule for completion in early June. The large carrying capacity of ‘Innovation’, efficient jacking operations and smooth offshore bolting operations lead to record installation cycles," DEME said.

“Together with Ørsted, we will continue our excellent partnership for the remaining foundations. I also would like to take this opportunity to thank the client, our crew and project staff for the great achievement, considering the unprecedented challenges they were all facing,” says Bart De Poorter, General Manager DEME Offshore.

The Borssele 1 & 2 offshore wind farm will be completed in 2020.

Current News

Russian Gas Exports to Europe Rise 20% in 2024

Russian Gas Exports to Europe

TotalEnergies to Keep DeepSea Mira Rig in West Africa

TotalEnergies to Keep DeepSea

OE’s 2024 Top of the Festive Video Pops

OE’s 2024 Top of the Festive V

Offshore Drilling 2025: 3 Things to Watch During a Year of Market Corrections

Offshore Drilling 2025: 3 Thin

Subscribe for OE Digital E‑News

Offshore Engineer Magazine