PG Flow Solutions Pumps Selected for Aker BP's Hod

PG Flow Solutions has won a contract to supply pump systems for AKER BP's normally unmanned wellhead platform to be used at the planned Hod field development in the North Sea, offshore Norway.

Aker BP last week made the final investment decision for the Hod project. The platform will be built by Kvaerner.

PG Flow Solutions said the contract award followed an agreement between a broad political majority in Norway to make temporary changes to the Norwegian petroleum tax system. The Hod development in the Valhall area is Aker BP’s first project to be launched as a direct result of the tax changes.

Steve Paulsen, CEO of PG Flow Solutions: “It is reassuring to see that operators stay true to their word and initiate projects that were put on hold as a consequence of the extraordinary negative effects caused by the Covid-19 outbreak. New projects allow us, as a supplier, to continuously evolve our offering in order to help make field developments more competitive and to increasingly apply this competence in other industries, such as aquaculture, fisheries and renewables, as we have done over the past decade."

The planned wellhead platform to be named “Hod B” is the second project in the Wellhead Platform Alliance, which was established in 2017 by Aker BP, Kvaerner, ABB and Aker Solutions. The alliance’s first project was the successful Valhall Flank West field development, including its normally unmanned wellhead platform which came on stream in 4Q 2019.



Under the contract, PG Flow Solutions will deliver miscellaneous pumps to the platform topside, including a pressure-equalizing pump, fresh water pump, fresh water pressure pump, diesel transfer pump, and one hazardous open-drain pump.

PG Flow Solutions has not disclosed the value of the contract, which is subject to government approval of the plan for development and operations (PDO). The company will manage the project out of its facility in Sande, Vestfold, Norway.

Similar to Valhall order

The contract is almost identical to the pump system delivery that PG Flow Solutions made to Aker BP and the Wellhead Platform Alliance for the Valhall Flank West wellhead platform in 2018, PG Flow Solutions said.

“Re-using already proven solutions and development plans reduce costs and risks for both suppliers and the operator. We are therefore very comfortable with the scope of work and delivery schedule indicated for the Hod platform too,” says Mark Tuinman, sales manager – energy, at PG Flow Solutions.

The new Hod platform concept is basically a copy of the Valhall Flank West platform design, with minor changes to functional requirements and some changes resulting from lessons learned from the Valhall Flank West design, commissioning and handover phases.

The Hod field was discovered in 1974; first oil came onstream in 1990 as a tie back to Valhall Central Complex, producing via a wellhead platform until 2013. The Hod field development project is now working towards a new development of the Hod field, planning to install a new normally unmanned platform that will be tied-back to and remotely controlled from the Valhall Central Complex.  

The Hod field is located in Block 2/11 in the southern part of the Norwegian sector of the North Sea, approximately 12 km south of Valhall Central Complex, 6 km south of the Valhall Flank South platform. The operator is Aker BP AS, holding 90 percent working interests, with Pandion Energy AS as the sole license partner holding the remaining 10 percent.

Current News

Danos Leaders Recognized in “40 Under 40” Lists

Danos Leaders Recognized in “4

ExxonMobil to Drill for Gas Off Cyprus in January

ExxonMobil to Drill for Gas Of

Mocean Energy Raising Funds to Advance Wave Energy Tech

Mocean Energy Raising Funds to

Seadrill’s Drillships Getting Ready to Start Work Off Brazil

Seadrill’s Drillships Getting

Subscribe for OE Digital E‑News

Offshore Engineer Magazine