East Anglia ONE Offshore Wind Farm Project Complete

Credit: ScottishPower Renewables
Credit: ScottishPower Renewables

East Anglia ONE, a £2.5 billion offshore wind farm 43km off the coast of Suffolk, UK, has been completed, ScottishPower Renewables has informed.

All 102 Siemens Gamesa offshore wind turbines – situated 43km off the Suffolk coast – are now fully operational, with the capacity to produce 714MW of electricity.

Each year, the offshore wind farm, owned by ScottishPower Renewables and Green Investment Group, will produce enough electricity to power the equivalent of more than 630,000 homes.

"Around 20 percent of the turbine installation and around half the turbine connection work was completed during the lockdown, with ScottishPower Renewables and its project partners transforming how they worked to get the job done. This included switching to a higher number of smaller vessels, creating crew ‘households’ who lived and worked together at all times, introducing new welfare protocols, and minimizing crew changes," the company said.

According to ScottishPower Renewables, almost 3,500 jobs were sustained during the construction phase, which began in 2017, while 100 long-term skilled jobs have been created at the operations and maintenance base in Lowestoft.

Charlie Jordan, East Anglia ONE Project Director at ScottishPower Renewables, said: “The final commissioning of East Anglia ONE is an incredible milestone for us and our project partners, as well as our wider stakeholders, the East Anglian region and the whole of the UK. And it comes at a crucial time as the UK takes it first steps towards a green economic recovery."

Credit: ScottishPower Renewables

“Reaching this point was always going to be an extremely important moment for us – heralding the start of full production of green energy from a major site that will play a real part in the UK’s path to Net Zero.  What has made it even more incredible is the determination and tenacity of our team, who have worked tirelessly to deliver this significant technical project amidst an unprecedented pandemic, which none of us could have planned for. 

"This was also the first time we have worked with Green Investment Group, and I would like to thank them for their support.

"I am extremely proud of everyone involved who has helped to deliver the project, doing so in a safe manner. I am delighted East Anglia ONE will play a leading roll in the region’s green energy production, and will also become a hub of industry, investment and skills as we continue to build the green energy sector that’s so important for our future.”

Credit: ScottishPower Renewables

Edward Northam, Head of GIG Europe, said: “Successfully commissioning one of the world’s largest offshore windfarms on time, despite all of the challenges posed by Covid-19, is a testament to the incredible efforts of the whole East Anglia ONE team – and the many UK businesses that have supported the project. Many congratulations to all involved.



“East Anglia ONE is a reminder that the UK continues to lead the world in the successful delivery of offshore wind projects, and I’m proud of the role that Green Investment Group has played, and continues to play, in supporting and funding the development of this market. We remain committed to accelerating the UK’s energy transition and believe offshore wind will be at the heart of the UK’s net zero energy system.”

Andrew Elmes, East Anglia ONE Senior Project Manager at Siemens Gamesa, said: "The team reacted superbly to the COVID-19 pandemic, preventing East Anglia ONE from being derailed by the unprecedented situation."

He said: "Safety issues to be managed in a critical period included: complete vessel, accommodation, and crew reorganizations; quarantine events, social distancing, suspect cases, and testing onsite. We are extremely proud to have done so while achieving several key customer - and Siemens Gamesa - business milestones, despite the uncertainty. We’ve now commissioned the entire offshore wind power project, making real our commitment to providing clean energy for generations to come.”


Watch the recording of World Energy Report's Offshore Wind Webinar "Outlook for Offshore Wind Power: The Frontier of Future Energy."

Current News

ExxonMobil, Hess, CNOOC Withdraw from Guyana’s Oil Block Negotiations

ExxonMobil, Hess, CNOOC Withdr

Velesto Completes Removal of Wrecked Naga 7 Jack-Up Rig Off Malaysia

Velesto Completes Removal of W

Saudi Aramco Suspends Another Shelf Drilling Jack-Up

Saudi Aramco Suspends Another

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

BP Greenlights $7B CCUS Scheme

Subscribe for OE Digital E‑News

Offshore Engineer Magazine