Heerema Breaks Jacket Installation Record at Johan Sverdrup Field

Credit: Heerema Marine Contractors
Credit: Heerema Marine Contractors

Dutch offshore installation firm Heerema Marine Contractors said Wednesday its heavy lift vessel Sleipnir had broken records on the Johan Sverdrup Phase 2 development project in Norway.

"On June 18, Sleipnir successfully installed the 12,050 metric ton Johan Sverdrup processing platform (P2) jacket, setting a new record for the heaviest lift jacket installation. 

"This lift comes after the inshore integration of the three P2 topside modules on behalf of client Aibel at the GMC yard in Gismarvik in May. This mating process included the heaviest crane lift in Norwegian waters, with the MSF module weighing a massive 13,600 metric tons," Heerema Marine Contractors said. Credit: Heerema Marine Contractors

Johan Sverdrup is the biggest field development on the Norwegian continental shelf since the 1980s. The Johan Sverdrup Phase 2 development will capture the full potential of the giant Johan Sverdrup oil field on the Norwegian Continental Shelf. 

The new processing platform, which will be the second of its kind at the field center, will make for a total of five platforms when the development is completed.

Heerema said that the inshore mating of the P2 topside included integrating three modules weighing 13,500 metric tons, 5,400 metric tons, and 4,300 metric tons. 

"This successful operation was the result of close cooperation between Heerema, client Aibel, and operator Equinor. The modules were built in Thailand, Spain, and Norway and are Aibel's largest project ever. Now that the lifting operations are complete, the topside has been towed by Heerema's Kolga to Aibel's yard in Haugesund," Heerema said.Credit: Heerema Marine Contractors

"Thereafter, on behalf of client Equinor, Sleipnir lifted the 12,050 metric ton P2 jacket, which is the heaviest jacket in the world so far to be lifted directly from the transportation barge. This installation method made it possible to reduce the jacket weight considerably, compared to a more traditional launch jacket, resulting in significant fabrication cost savings," the company said.

'We are proud to play a part in Equinor's Johan Sverdrup P2 development, and to achieve two new lifting records in the process is always special. Both projects were successful due to the close cooperation with our clients, and we look forward to returning to the Johan Sverdrup field later this year’ says Michel Hendriks, Heerema's Transport and Installation Director.

Equinor, the operator of the Johan Sverdrup field recently upgraded output expectations, with full field gross production capacity of 755 thousand barrels of oil per day (Mbopd) expected once Phase 2 is on stream. Phase 2 remains on schedule for first oil in the fourth quarter 2022

Current News

OE’s 2024 Top of the Festive Video Pops

OE’s 2024 Top of the Festive V

Offshore Drilling 2025: 3 Things to Watch During a Year of Market Corrections

Offshore Drilling 2025: 3 Thin

Chevon’s Sanha Lean Gas Connection Project Achieves First Gas off Angola

Chevon’s Sanha Lean Gas Connec

BP and Partners Secure Rights for 450MW Offshore Wind Farm in Japan

BP and Partners Secure Rights

Subscribe for OE Digital E‑News

Offshore Engineer Magazine