PHOTO: First Jacket Installed at Neart na Gaoithe Offshore Wind Farm Site

©Neart na Gaoithe
©Neart na Gaoithe

The first wind turbine jacket foundation has been installed at the Neart na Gaoithe offshore wind farm, 15.5km off the east coast of Scotland.

Following the arrival of the first ten steel jackets on site, Saipem, through its subcontractor Heerema, lifted the first steel wind turbine jacket into place, lowering it onto pre-installed piles on the seabed.

The offshore support vessel Normand Navigator then moved into place to carry out subsea grouting and inspections to finish the installation.©Neart na Gaoithe 

Matthias Haag, NnG Project Director, said: "The installation of the first of a total of 54 turbine jacket foundations is a significant milestone for the NnG project and builds on the progress of the first of two offshore electricity substations installed in June this year. The collaborative effort in installing the jacket was a great success, and we remain on course for the others to be installed over the coming months."

NnG, jointly owned by EDF Renewables and ESB, will supply enough low carbon electricity for around 375,000 households. It has a capacity of around 450 megawatts (MW) of low carbon energy and will offset over 400,000 tonnes of CO2 emissions each year.

The first turbines should be up and running by mid-2023, and the whole wind farm should be completed by 2024.©Neart na Gaoithe 

Current News

OE’s 2024 Top of the Festive Video Pops

OE’s 2024 Top of the Festive V

Offshore Drilling 2025: 3 Things to Watch During a Year of Market Corrections

Offshore Drilling 2025: 3 Thin

Chevon’s Sanha Lean Gas Connection Project Achieves First Gas off Angola

Chevon’s Sanha Lean Gas Connec

BP and Partners Secure Rights for 450MW Offshore Wind Farm in Japan

BP and Partners Secure Rights

Subscribe for OE Digital E‑News

Offshore Engineer Magazine