U.S. Designates Offshore Wind Farm Development Areas in Gulf of Mexico

©BOEM
©BOEM

 The U.S. Gulf of Mexico, best known to the offshore energy industry as an oil and gas province, is for the first time opening its doors to the offshore wind industry, with the U.S administration on Monday designating two areas for offshore wind development in the region.

The U.S. Bureau of Ocean Energy Management (BOEM) on Monday said it had finalized two Wind Energy Areas (WEAs) in the Gulf of Mexico, with the potential to produce enough electricity to power nearly 3 million households.

The first WEA is located approximately 24 nautical miles (nm) off the coast of Galveston, TX. The area totals 508,265 acres and has the potential to power 2.1 million households. The second WEA is located approximately 56 nm off the coast of Lake Charles, LA. The area totals 174,275 acres and has the potential to power over 740,000 households, according to BOEM.

"This growing industry will provide Americans with cleaner and cheaper energy, create thousands of good-paying jobs, and invest billions in new American energy supply chains, manufacturing, shipbuilding and servicing," BOEM said.

BOEM explained that it uses its renewable energy competitive leasing process to identify the offshore locations that appear most suitable for development, taking into consideration potential impacts to resources and ocean users.

"BOEM collaborated with the National Oceanic and Atmospheric Administration to build an ocean model that analyzed the entire Gulf of Mexico ecosystem to find areas that have the least conflict with other uses and the lowest environmental impact," BOEM said.

“These two wind energy areas represent exciting progress toward having the first offshore wind lease sale in the Gulf of Mexico, where there is a mature industry base and the know how to advance energy development in the OCS. The Region can play a central role in our nation’s clean energy transition to support good paying jobs, fight climate change,” said BOEM Director Amanda Lefton. “BOEM will continue to work with the coastal states and communities as we advance our work and do so in a manner that seeks to avoid or minimize conflicts with other ocean uses and marine life in the Gulf of Mexico.”

In July 2022, the Department of the Interior said that BOEM was seeking input on two draft WEAs during a 30-day public comment period. 

"Due to feedback received during a Gulf of Mexico Renewable Energy Task Force meeting, BOEM extended the comment period to 45 days, which closed on September 2, 2022. BOEM received 107 comments, which helped inform the final WEAs," BOEM said.

BOEM slightly reduced the size of the WEAs from their draft versions to address concerns expressed by the Department of Defense and the U.S. Coast Guard regarding shipping, marine navigation, and military operations, BOEM explained.

The next steps in BOEM’s renewable energy competitive leasing process include issuing a Proposed Sale Notice with a 60-day public comment period later this year or early next year.

The U.S. plans to have 30 gigawatts of offshore wind energy capacity installed by 2030.

Current News

BOEM Okays New England Offshore Wind Project

BOEM Okays New England Offshor

Solstad Offshore Bolsters Ownership Stake in Omega Subsea

Solstad Offshore Bolsters Owne

DeepOcean Takes Over Equinor’s Pipeline Repairs Contract from TechnipFMC

DeepOcean Takes Over Equinor’s

Petrobras Steps Closer to Developing Hydrogen Plant Powered by Renewables

Petrobras Steps Closer to Deve

Subscribe for OE Digital E‑News

Offshore Engineer Magazine