BlueNord, the partner in the Tyra II project along with TotalEnergies and Nordsøfonden, has informed that the onshore repair of the second transformer for Tyra II is progressing well, with full technical capacity of Denmark’s largest offshore…
The operator of the Danish Underground Consortium, TotalEnergies, has informed its partners that all necessary machinery is now fully operational at the new Tyra facilities.This milestone marks the achievement of full technical capacity, which…
BlueNord, the partner in the Tyra II project along with TotalEnergies and Nordsøfonden, has informed that Tyra II facilities will start operating at maximum technical capacity in the first half of November 2024, following the completion of equipment repairs…
TotalEnergies, the operator of the Tyra II project on behalf of consortium partners, has faced another technical issue during the commissioning of Denmark’s largest offshore gas development.TotalEnergies, the operator of the Danish Underground Consortium in charge of Tyra II redevelopment…
TotalEnergies has discovered additional gas condensate resources in the new well at the Harald field in the Danish North Sea, which could start producing through the existing Harald and Tyra facilities before the end of 2024.Located in shallow waters…
Operator TotalEnergies has repaired the intermediate pressure compressor transformer at Tyra II that was subject to an operational occurrence in April 2024 which delayed ramp-up to maximum capacity.It was repaired onshore and is now back at the Tyra facilities offshore Denmark…
The Tyra Redevelopment Project (Tyra II) continues to progress according to plan with the start of processing and export of gas from the Tyra Satellite Harald field.The gas export from the Tyra Satellite Harald field was achieved in the evening of April 10…
The technical issue, which has temporarily impacted the commissioning of the facilities at Denmark’s largest offshore gas development, has been identified with repair works currently ongoing as the timeline for reaching Tyra II full technical capacity gets delayed for the third quarter of 2024…
The Tyra Redevelopment Project (Tyra II), operated by TotalEnergies, has faced an operational occurrence which has temporarily impacted the commissioning of the facilities at Denmark’s largest offshore gas development.According to an update from TotalEnergies…
The operational occurrence which has temporarily impacted the commissioning of the Tyra Redevelopment Project (Tyra II) has pushed the planned ramp-up of the facilities to full capacity for one month.An operational occurrence related to the…
The Tyra Redevelopment Project (Tyra II) has restarted production. At plateau, the Tyra hub will produce 5.7 million cubic meters of gas and 22,000 barrels of condensate per day.TotalEnergies operates the Tyra field on behalf of Danish Underground Consortium…
Norway-based oil and gas company BlueNord has started drilling operations at the Harald East Middle Jurassic well (HEMJ), which could start delivering gas by the end of 2024, set to be exported through the Tyra East facilities.The HEMJ was spudded in the Harald East area…
TotalEnergies has informed that the restart of production from the Tyra facilities is progressing according to plan, with the first gas expected to be exported to the Danish market from the new Tyra II system on March 28, 2024.TotalEnergies…
BlueNord, a partner in the TotalEnergies-operated Tyra natural gas development, has announced that the methanol loading at the redevelopment project has started, with the official restart set for the second half of March.Following the milestone and depending on continued progress…
Denmark's Tyra natural gas field remains on track to restart production by the end of March, BlueNord, a partner in the TotalEnergies-operated development, said on Tuesday.Denmark's largest gas field, which was temporarily shut for redevelopment in 2019…